Atlantic Coast Pipeline Delayed As Costs Rise

dominion energy

FAYETTEVILLE, N.C. (AP) - The completion of a natural gas pipeline running through West Virginia, Virginia and North Carolina has been delayed and its costs are increasing by up to $3 billion.

The Fayetteville Observer reports Atlantic Coast Pipeline LLC announced Friday that the 600-mile (965-kilometer) pipeline is not expected to be in full service until 2021. It was initially expected to be in service this year.

The project was projected to cost between $4.5 billion and $5 billion when first announced. Now the company projects a total cost of $7 billion to $7.5 billion.

A spokesman for pipeline partner Dominion Energy, Karl Neddenien, blames delays for the cost increases. Some work was suspended last year over questions related to a national permit, while residents and environmental groups have sued to stop the project.

Don Rush is the News Director and Senior Producer of News and Public Affairs at Delmarva Public Media. An award-winning journalist, Don reports major local issues of the day, from sea level rise, to urban development, to the changing demographics of Delmarva.